4 October 2018, TWT Property Group, together with Parkview, hosted NewLife Darling Harbour Core C & D Topping Out Ceremony. This included many of the consultants involved in the project including the architects and designers.
NewLife Darling Harbour has reached its highest point on the Bulwara Road side (Building Core C & D). The Interior construction of these two buildings has progressed smoothly: structure of interior walls and pipeline have been built up to level 4 with interior fit out proceeded to level 1. Facade masonry has progressed to level 2 so far.
The East side adjacent to Harris Street (Building Core A & B) is complete to level 4. The next phase of work is continuing with the construction of upper levels and interior walls.